Structured at a post-money valuation of roughly 50million(28 million pre-money), the transaction grants Nocera board representation and governance rights over major corporate matters. All proceeds are dedicated exclusively to building BitRock’s inaugural 10-megawatt (MW) natural-gas-powered AI data center on a 37-acre industrial campus near Hanna, Alberta.
Completing a Four-Layer AI Stack
BitRock represents the fourth foundational pillar in an AI infrastructure platform Nocera has assembled through targeted agreements since June 2026:
-
AI Software: A binding venture platform agreement signed in June with U.S.-based Digital Innovations Group (developer of the IRMA AI Engine), slated to close prior to year-end 2026.
-
Energy Storage: A July agreement to acquire an equity stake in power storage platform INERGX, followed in August by the creation of a 50/50 joint venture, Nocera-INERGX Energy Ventures.
-
Memory & Storage Distribution: The July acquisition of a 30% controlling interest in Taiwan-based Micron/Crucial authorized distributor QMAX Technology Co., Ltd.
-
Self-Powered Compute Capacity: The proposed 44% stake in BitRock.
“This is a measured entry into North American compute with a meaningful ownership position and a voice on the board,” said Andrew Teng, Asia Director of Nocera, noting that BitRock’s self-generated natural gas model directly addresses grid capacity bottlenecks in Alberta, where the provincial grid operator has fully allocated its interim 1,200 MW large-load capacity.
Modular Rollout and Colocation Focus
Rather than deploying capital into rapidly depreciating GPU hardware, Nocera’s investment funds physical energy and colocation infrastructure. BitRock will provide powered data hall capacity and operations while enterprise clients install their own computing equipment, backed by memoranda of understanding already signed by prospective hosting customers, according to BitRock’s representations.
The initial 10 MW facility comprises four prefabricated 2.5 MW modules engineered to a target power usage effectiveness (PUE) of approximately 1.225 with N+1 redundancy, utilizing Alberta’s cold climate to lower cooling overhead. While BitRock’s long-term campus blueprint envisions scaling to 200 MW in 10 MW increments, future phases will be evaluated and financed separately.
Funding remains subject to customary closing conditions over a 60-day diligence window (extendable by 30 days), including execution of a definitive agreement, regulatory approvals, and pre-money valuation protections should due diligence uncover material deviations from BitRock’s representations.