U.S. Forest Service pauses timeline for Rio Tinto Arizona copper mine

Published 05/19/2023, 02:16 PM
Updated 05/19/2023, 03:36 PM
© Reuters. FILE PHOTO: Apache Stronghold, a Native American group hoping to protect their sacred land from a Cooper mine in Arizona, gather outside the 9th Circuit Appeal Court in Pasadena, California,U.S., March 21, 2023.        REUTERS/Mike Blake

By Ernest Scheyder

(Reuters) - The U.S. Forest Service has told a federal court it is not sure when it could approve a land swap allowing Rio Tinto (NYSE:RIO) Plc to develop the Resolution Copper mine in Arizona, a surprising reversal that boosts several Native American groups opposed to the project.

The complex case involves a long-running conflict between a mining company hoping to supply more than a quarter of U.S. copper demand for the green energy transition and Indigenous groups seeking to preserve Arizona's Oak Flat campground, a site of religious importance that would be destroyed by the mine's construction.

In 2014, the U.S. Congress approved a land swap that required an environmental report to be published, which former President Donald Trump's administration did shortly before leaving office. President Joe Biden unpublished that report in March 2021 to give his administration time to review concerns from Native Americans, though he was not able to permanently block the mine.

The case has wound its way through several courts. Joan Pepin, an attorney for the Forest Service, told judges during a March hearing the report would be republished "this spring."

Rumors have swirled in recent weeks that the Biden administration was on the verge of re-publishing that report, and several Rio executives made plans to travel to Arizona next week.

Late Thursday night, though, Pepin sent a letter to the court saying government officials were still meeting with Native American tribes.

"The department has not yet identified a timeframe for completing its review," Pepin said.

3rd party Ad. Not an offer or recommendation by Investing.com. See disclosure here or remove ads .

Neither Pepin nor other U.S. Forest Service officials could be reached for additional comment.

Previously, officials had said they would alert the court at least 60 days before re-publishing the report. Once re-published, officials would have an additional 60 days to transfer the land to Rio Tinto.

Rio Tinto said it would continue to try to talk with tribes and believes there is significant local support for the mine. "Our team is ready to advance the project in collaboration with Native American tribes, local communities, and labor," said Vicky Peacey, general manager of the Resolution project.

BHP Group (NYSE:BHP) Ltd, which is helping Rio develop the mine, declined to comment.

"It's quite unusual for the government to have to take back something their attorney told the court under questioning," said Luke Goodrich of Becket Law, a religious liberty legal group involved in the case.

Representatives for the San Carlos Apache tribe have vowed that if they lose, they will appeal the ruling to the U.S. Supreme Court.

"There is overwhelming opposition in Indian Country to the Resolution mine and that will not change," said Terry Rambler, San Carlos Apache tribal chairman.

Local officials who support the project said they were angered by Pepin's letter.

"Every time there's another delay to this process means that investors in our community may decide this isn't the place to invest because the federal government can't make up its mind," said Mila Besich, the Democratic mayor of Superior, a town of 2,500 that abuts the mine site.

3rd party Ad. Not an offer or recommendation by Investing.com. See disclosure here or remove ads .

Latest comments

Liberty for you those who stole it. By lying to collect.
Risk Disclosure: Trading in financial instruments and/or cryptocurrencies involves high risks including the risk of losing some, or all, of your investment amount, and may not be suitable for all investors. Prices of cryptocurrencies are extremely volatile and may be affected by external factors such as financial, regulatory or political events. Trading on margin increases the financial risks.
Before deciding to trade in financial instrument or cryptocurrencies you should be fully informed of the risks and costs associated with trading the financial markets, carefully consider your investment objectives, level of experience, and risk appetite, and seek professional advice where needed.
Fusion Media would like to remind you that the data contained in this website is not necessarily real-time nor accurate. The data and prices on the website are not necessarily provided by any market or exchange, but may be provided by market makers, and so prices may not be accurate and may differ from the actual price at any given market, meaning prices are indicative and not appropriate for trading purposes. Fusion Media and any provider of the data contained in this website will not accept liability for any loss or damage as a result of your trading, or your reliance on the information contained within this website.
It is prohibited to use, store, reproduce, display, modify, transmit or distribute the data contained in this website without the explicit prior written permission of Fusion Media and/or the data provider. All intellectual property rights are reserved by the providers and/or the exchange providing the data contained in this website.
Fusion Media may be compensated by the advertisers that appear on the website, based on your interaction with the advertisements or advertisers.
© 2007-2024 - Fusion Media Limited. All Rights Reserved.