Get 40% Off
🚨 Volatile Markets? Find Hidden Gems for Serious Outperformance
Find Stocks Now

Germany's wind power expansion stalls on the roads

Published 09/07/2023, 03:22 AM
Updated 09/07/2023, 06:27 AM
© Reuters. A view shows a sign for a heavy haulage convoy during transport of a nacelle of a wind turbine near a wind farm, in Biegen, Germany August 31, 2023. REUTERS/Lisi Niesner

By Riham Alkousaa

BERLIN (Reuters) - Germany's wind power expansion is facing an unexpected roadblock: builders need permits to transport the heavy turbines down the country's roads, and they are waiting months to get them.

With a backlog of more than 15,000 applications for approvals, companies say their projects are heavily delayed, with the costs of prolonged warehousing for steel tower segments, generators and blades running into the millions.

"Assuming nothing changes, it could cost 115 million euros extra by the end of the year," Felix Rehwald, a spokesperson for wind turbine manufacturer Enercon, told Reuters.

Transport permits are needed to drive heavy loads over bridges and highways. Sometimes structures and road signs need dismantling, and police escorts are needed for some loads, while others can only be sent at night.

"It is currently one of the most pressing challenges for us and our competitors," Rehwald added.

Delays in securing permits were costing the company thousands of euros per day, Rehwald said, adding that bottlenecks could only get tighter as wind construction ramps up towards the middle of next year.

Germany aims to obtain 80% of its electricity from renewable sources by 2030, 115 gigawatts of which should come from onshore wind, but a lack of transport permits endanger that goal.

Nordex, a global leader in wind turbine manufacturing, told Reuters that parking spots for its lorries are too scarce and that the cost of permits has risen as much as tenfold, with a spokesperson talking of "massive delays and significant costs."

3rd party Ad. Not an offer or recommendation by Investing.com. See disclosure here or remove ads .

The cost of applications had jumped to more than 1,000 euros per permit in 2021 from 100 euros, Nordex said. But permits were so rigid in their scope that companies often made multiple applications to cover for different eventualities.

"I can't apply for a transport permit and tomorrow say: 'I'll drive the green truck instead of the red', because a new permit is needed," Kai Westphal, a regional head of transport at Wind turbine maker Vestas, told Reuters.

Some 150 permits are needed on average for transporting a wind turbine, 100 to 120 for cranes, and 60 for turbine components, a study by engineering association VDMA published last year showed.

Without a single law regulating heavy load transport, each federal state requires different documents, the study added.

Documents are submitted using software that dates from 2007 and according to general guidelines that date back to 1992 but each authority has its own administrative regulations for permit applications, VDMA researcher Sebastian Steul said.

"We need a geo-information system as soon as possible that combines the handling of all processes related to large and heavy transport that can be used by both the industry and the authorities," Steul said.

The steep rise in the number of applications resulting from the wind power ramp-up is contributing to delays, as is the poor condition of some bridges and roads and different interpretations of the regulations by authorities, he said.

A 2021 restructuring of the authority that examines the applications has complicated the problem, companies said, blaming untrained and unresponsive staff and a new software tool the government-owned Autobahn GmbH company uses for examining applications.

3rd party Ad. Not an offer or recommendation by Investing.com. See disclosure here or remove ads .

Autobahn GmbH said approvals were the responsibility of federal states and it only provided an expert opinion on navigability of a requested route.

The government-owned company said it was doing everything to speed up the process but examining the transport of wind turbines' rotor blades was particularly demanding due to their extraordinary length. A nationwide, standardized and largely automated process should be in place by the end of 2023, it said.

Germany's government on Wednesday announced plans for a raft of measures designed to stimulate the economy by reducing bureaucracy, speeding up approval processes for new construction and digitizing citizens' access to key government services.

The so-called Germany Pact sets out a range of goals to be achieved in consultation with powerful regional governments including swifter, online consultation processes for wind farms and transport and data networks, a government document showed.

In the meantime, processing each permit will take up to three months in Germany, compared with an average of two to three weeks in the Netherlands and around 10 days in Denmark.

Having specially trained drivers and pilots for the entire fleet of such big deliveries has accelerated the process in Denmark as authorities don't require a police escort for each transfer any more, said Morten Arnskov Boejesen, a senior advisor for Confederation of Danish Industry.

The Danish Road Directorate took over this responsibility from the police in Oct. 2021 and both the industry and the authority seem to be pleased with how the process is being handled, said to Soren Andersen, Area manager in The Danish Road Directorate.

3rd party Ad. Not an offer or recommendation by Investing.com. See disclosure here or remove ads .

"It's definitely easier in Denmark; you get an application through in a week … we can only dream of this here," Westphal added.

Latest comments

Risk Disclosure: Trading in financial instruments and/or cryptocurrencies involves high risks including the risk of losing some, or all, of your investment amount, and may not be suitable for all investors. Prices of cryptocurrencies are extremely volatile and may be affected by external factors such as financial, regulatory or political events. Trading on margin increases the financial risks.
Before deciding to trade in financial instrument or cryptocurrencies you should be fully informed of the risks and costs associated with trading the financial markets, carefully consider your investment objectives, level of experience, and risk appetite, and seek professional advice where needed.
Fusion Media would like to remind you that the data contained in this website is not necessarily real-time nor accurate. The data and prices on the website are not necessarily provided by any market or exchange, but may be provided by market makers, and so prices may not be accurate and may differ from the actual price at any given market, meaning prices are indicative and not appropriate for trading purposes. Fusion Media and any provider of the data contained in this website will not accept liability for any loss or damage as a result of your trading, or your reliance on the information contained within this website.
It is prohibited to use, store, reproduce, display, modify, transmit or distribute the data contained in this website without the explicit prior written permission of Fusion Media and/or the data provider. All intellectual property rights are reserved by the providers and/or the exchange providing the data contained in this website.
Fusion Media may be compensated by the advertisers that appear on the website, based on your interaction with the advertisements or advertisers.
© 2007-2024 - Fusion Media Limited. All Rights Reserved.