Get 40% Off
👀 👁 🧿 All eyes on Biogen, up +4,56% after posting earnings. Our AI picked it in March 2024.
Which stocks will surge next?
Unlock AI-picked Stocks

British Columbia boosts power plan but electrifying LNG proving big challenge

Published 01/20/2024, 12:44 PM
Updated 01/20/2024, 12:45 PM
© Reuters. FILE PHOTO: LNG Canada site construction activities are held, in Kitimat, Canada, September 2022. LNG Canada/Handout via REUTERS/File Photo

(This Jan. 19 story has been corrected to fix the affiliation of source to Clean Energy Canada, not Clean Energy BC, in paragraph 17)

By Rod Nickel

WINNIPEG, Manitoba (Reuters) - British Columbia boosted its C$36 billion ($26.7 billion) plan to expand its grid over the next decade, but Canada's Pacific Coast province will still fall short of supplying the biggest liquefied natural gas (LNG) projects with hydropower needed to avoid generating high emissions.

Long regulatory processes mean a critical northern transmission line expansion will only be ready years after LNG plants start operating and droughts are already curbing British Columbia's (B.C.'s) power generation.

B.C. boosted its electricity grid spending plans on Tuesday by 50%, as demand soars from industry for renewable hydropower and as the province switches to electric vehicles and electric heating in buildings.

"It's a huge challenge to meet all the potential demand for electricity - daunting," said Barry Penner, a former B.C. environment minister and now chair of Energy Futures Initiative, a program of advocacy group Resource Works.

Supplying hydropower to LNG projects, including Shell-led LNG Canada, is critical to the goals of the province and Canada to cut emissions sharply by 2030. LNG export facilities would tap into lucrative offshore demand for Canadian natural gas.

LNG Canada, which is 90% complete, will run its 14 million-metric ton per annum facility on high-emission natural gas, complicating Canada's net-zero goals. The company, which is considering a second phase that may switch to grid power once it's available, said in a statement on Thursday it is encouraged by government efforts to expedite electricity expansion.

3rd party Ad. Not an offer or recommendation by Investing.com. See disclosure here or remove ads .

The key part of B.C.'s grid plan for LNG Canada is the C$3 billion expansion of a northwest transmission line. Building it would take up to 10 years because of the need for agreement with First Nations and permitting, BC Hydro CEO Chris O'Riley said.

"We're all committed to getting these projects built as quickly as possible and we all want them to run on electricity. That's our goal," O'Riley said in an interview.

BC Hydro's timeline means the transmission line won't be expanded until the early 2030s, after LNG Canada and rival proposals Ksi Lisims LNG and Cedar LNG are running.

FIRST NATIONS SUPPORT

A capacitor station project in northwestern B.C. will provide sufficient power for Cedar LNG, a project of the Haisla Nation and Pembina Pipeline (NYSE:PBA), O'Riley said. Ksi Lisims plans to start up as early as 2028.

First Nations support for the northwest transmission line could accelerate the regulatory timeline. K'uul Power, a consortium of 11 First Nations, is in talks to buy 50% of the project from BC Hydro.

"If you're in charge, then you're OK with going fast because you can protect your interests," said K'uul CEO Alex Grzybowski. "An expedited process is entirely on the table."

B.C. has formed a task force to speed up permitting for clean energy projects.

B.C., like Quebec, whose government-owned Hydro Quebec utility released its own long-term plan for grid expansion in November, relies on hydro for most of its power. That resource and B.C.'s coastal ports have made it the center of Canada's nascent LNG industry. Neighboring Alberta by contrast relies on high-emission natural gas to generate power.

3rd party Ad. Not an offer or recommendation by Investing.com. See disclosure here or remove ads .

Droughts pose another challenge for B.C. BC Hydro imported a record one-fifth of its 2023 power needs as drought cut hydropower generation.

BC Hydro plans to add wind and solar generation to help hedge the drought risk, O'Riley said.

But B.C. may still lack sufficient power to satisfy all industries, from LNG to mining of critical minerals and hydrogen proposals, said Evan Pivnick, program manager at Clean Energy Canada.

"One of the key questions that B.C. is going to have to confront is, which industries is it prioritising?" Pivnick said.

($1 = 1.3511 Canadian dollars)

Latest comments

long story short, Fossil fuels are here to stay
Natural gas is higher emission, but still a much cleaner burning fuel compared to diesel and coal.  And if it's used to offset electricity that goes into electric vehicles I imagine it's still better than just gas burning vehicles and is very economical.  Makes and excellent transitional fuel, but it is not good enough to appease the naive supporters of the bureaucrats and politicians.
Risk Disclosure: Trading in financial instruments and/or cryptocurrencies involves high risks including the risk of losing some, or all, of your investment amount, and may not be suitable for all investors. Prices of cryptocurrencies are extremely volatile and may be affected by external factors such as financial, regulatory or political events. Trading on margin increases the financial risks.
Before deciding to trade in financial instrument or cryptocurrencies you should be fully informed of the risks and costs associated with trading the financial markets, carefully consider your investment objectives, level of experience, and risk appetite, and seek professional advice where needed.
Fusion Media would like to remind you that the data contained in this website is not necessarily real-time nor accurate. The data and prices on the website are not necessarily provided by any market or exchange, but may be provided by market makers, and so prices may not be accurate and may differ from the actual price at any given market, meaning prices are indicative and not appropriate for trading purposes. Fusion Media and any provider of the data contained in this website will not accept liability for any loss or damage as a result of your trading, or your reliance on the information contained within this website.
It is prohibited to use, store, reproduce, display, modify, transmit or distribute the data contained in this website without the explicit prior written permission of Fusion Media and/or the data provider. All intellectual property rights are reserved by the providers and/or the exchange providing the data contained in this website.
Fusion Media may be compensated by the advertisers that appear on the website, based on your interaction with the advertisements or advertisers.
© 2007-2024 - Fusion Media Limited. All Rights Reserved.