Olympics: Tokyo 2020 venues on track for completion, say organizers

Published 02/12/2019, 06:17 AM
Updated 02/12/2019, 06:17 AM
© Reuters. A general view of the construction site of the Sea Forest Waterway for Tokyo 2020 Olympic and Paralympic games in Tokyo

By Jack Tarrant

TOKYO (Reuters) - Tokyo 2020 Olympic and Paralympic venues remain on track to be completed in time for test events scheduled for later this year, according to Games organizers.

Test events for sailing and water polo have already been held but the main bulk to testing is due to begin this summer, including at venues purpose built for the Games.

Other than the Olympic Stadium and the Olympic and Paralympic athletes village, Tokyo Metropolitan Government (TMG) is building eight new competition venues for the Games.

Many of the events are scheduled to be held at pre-existing venues in a bid to keep costs down.

During a media venue tour on Tuesday, organizers from the TMG said construction goals were being met.

"Each arena is preparing for the test events scheduled for around summer and construction is proceeding smoothly," Tomohiro Terasawa, venue director for the Ariake Arena, told Reuters.

"We're working hard to ensure everything is on time."

The Ariake Arena, which will host volleyball and wheelchair basketball, is 51 percent completed as on January 2019, the organizers informed.

The Tokyo Aquatics Center, which will host swimming and diving, is also over half completed while the Sea Forest Waterway, due to hold a rowing test event as early as August, is almost 80 percent finished.

There have been fears over the venue for tennis at the Tokyo 2020 Games, after the contractor hired to renovate parts of the Ariake Tennis Park went bankrupt in October.

However, the TMG has found a new contractor to work on re-building 17 outdoor courts that should be ready in time for the Olympics.

"For tennis, one part of the construction was delayed," said Terasawa. "One company's business was doing badly and it went under. The site reviewed its order and currently a new company is doing the construction."

The All Japan Tennis Championships, to be held in October, will serve as the test event for tennis.

© Reuters. A general view of the construction site of the Sea Forest Waterway for Tokyo 2020 Olympic and Paralympic games in Tokyo

Organizers are confident that renovations to the show court at Ariake, which usually hosts the annual Japan Open, will be ready by that time with minor delays only impacting the outdoor courts.

Latest comments

Risk Disclosure: Trading in financial instruments and/or cryptocurrencies involves high risks including the risk of losing some, or all, of your investment amount, and may not be suitable for all investors. Prices of cryptocurrencies are extremely volatile and may be affected by external factors such as financial, regulatory or political events. Trading on margin increases the financial risks.
Before deciding to trade in financial instrument or cryptocurrencies you should be fully informed of the risks and costs associated with trading the financial markets, carefully consider your investment objectives, level of experience, and risk appetite, and seek professional advice where needed.
Fusion Media would like to remind you that the data contained in this website is not necessarily real-time nor accurate. The data and prices on the website are not necessarily provided by any market or exchange, but may be provided by market makers, and so prices may not be accurate and may differ from the actual price at any given market, meaning prices are indicative and not appropriate for trading purposes. Fusion Media and any provider of the data contained in this website will not accept liability for any loss or damage as a result of your trading, or your reliance on the information contained within this website.
It is prohibited to use, store, reproduce, display, modify, transmit or distribute the data contained in this website without the explicit prior written permission of Fusion Media and/or the data provider. All intellectual property rights are reserved by the providers and/or the exchange providing the data contained in this website.
Fusion Media may be compensated by the advertisers that appear on the website, based on your interaction with the advertisements or advertisers.
© 2007-2024 - Fusion Media Limited. All Rights Reserved.